Jan 1, 2024
Suction Piles and Manifolds for the TPAO Sakarya gas field

Suction Piles and Manifolds for the TPAO Sakarya gas field
Global Energy Group’s fabrication division completed a contract with OneSubsea UK for the TPAO Sakarya gas field. The contract, which took place at our Port of Nigg facility over a 12-month period, consisted of the fabrication of two MEG suction piles, two production suction piles, two MEG distribution manifolds, and two production manifolds.
The suction piles were transported to the Black Sea where they were installed on the seabed, ready and waiting for the manifolds.
Between all of the structures, there was a total fabrication weight of approx. 1,200 tonnes.