Fabrication and Assembly of PAU Components for Worley on behalf of Ithaca Energy

Fabrication and Assembly of PAU Components for Worley on behalf of Ithaca Energy
Global Energy Group completed PAU component fabrication and coating, including the assembly of multiple PAUs into a singular module. This complex project included the installation of interconnected spools & steelwork, access staircases and module base frame.
The associated Electrical and Instrumentation (E&I) was installed and pre-commissioned by GEG, in addition to flange management and the hydrotesting & leak testing of all pipework and equipment.
Once complete, the assets were moved to the adjacent Clipper Quay at the Port of Aberdeen, for direct loadout onto the company vessel.